Linfield Christian School
Project Type:
Design/Build, Expansion/Remodel
Project Architect:
Brian R. Bloom, A.I.A.
Contractor/Builder: Tovey/Shultz
Construction, Inc.
Project Description:
The project consists
of multiple phases to be completed over a ten year period.
Phase one consisted of design and construction of theentrance
loop and underground infrastructure. Phase two included remodeling of the
existing high school
Buildings and construction of a new two story classroom building.
The third phase is the planning, design andconstruction of
the new high school, maintenance facility and play fields.
The high school will have state of the Art Technology
classrooms for advanced levels of learning.
Phase four will include major site improvements with theaddition
of baseball fields, landscaping throughout the site and reconfiguration of
the lake. Phase five will
consistof
tenant improvements of the old high school into a middle school as the high
school students move to their newfacility.
Future phases include the construction of a new administration building,
amphitheater, and athletic facilities.
Completion Date: Current Phase: September 2006